A strategy to identify breakdown location in MITICA test facility: results of high voltage test campaign
Authors:
Loris Zanotto,
Marco Boldrin,
Giuseppe Chitarin,
Mattia Dan,
Tommaso Patton,
Francesco Santoro,
Vanni Toigo,
Hiroyuki Tobari,
Atsushi Kojima,
Hans Decamps
Abstract:
The Acceleration Grid Power Supply of the MITICA test facility in Padova (Italy) is currently under commissioning. The power conversion system, the DC generator, and the High Voltage equipment have been individually commissioned, whereas the integration tests are ongoing. It is a challenging process due to the unconventional application, to the variety of different electrical technologies involved…
▽ More
The Acceleration Grid Power Supply of the MITICA test facility in Padova (Italy) is currently under commissioning. The power conversion system, the DC generator, and the High Voltage equipment have been individually commissioned, whereas the integration tests are ongoing. It is a challenging process due to the unconventional application, to the variety of different electrical technologies involved and to the complexity of the interfaces. During the integrated tests of the power supplies the achievement of 700kV stable operation has been demonstrated for the first time in a Neutral Beam Injector, but an unexpected event occurred, most likely a breakdown in the HV part, which resulted in a fault of the DC generator. A subsequent test using an auxiliary power supply was performed to check the voltage withstanding capability of the HV plant, but another breakdown occurred at around 1MV. This paper describes the activity performed to identify the location of the breakdowns affecting the integrated tests. A test campaign has been devised with increased diagnostic capabilities and specific strategy conceived to trigger intentional breakdowns in specific locations and collect measurement patterns for different cases. The results of the campaign will be presented and the current understanding of the issue will be described, with a view on future tests and further improvements of diagnostics.
△ Less
Submitted 26 April, 2023;
originally announced April 2023.
Lessons learned after three years of SPIDER operation and the first MITICA integrated tests
Authors:
D. Marcuzzi,
V. Toigo,
M. Boldrin,
G. Chitarin,
S. Dal Bello,
L. Grando,
A. Luchetta,
R. Pasqualotto,
M. Pavei,
G. Serianni,
L. Zanotto,
R. Agnello,
P. Agostinetti,
M. Agostini,
D. Aprile,
M. Barbisan,
M. Battistella,
G. Berton,
M. Bigi,
M. Brombin,
V. Candela,
V. Candeloro,
A. Canton,
R. Casagrande,
C. Cavallini
, et al. (117 additional authors not shown)
Abstract:
ITER envisages the use of two heating neutral beam injectors plus an optional one as part of the auxiliary heating and current drive system. The 16.5 MW expected neutral beam power per injector is several notches higher than worldwide existing facilities. A Neutral Beam Test Facility (NBTF) was established at Consorzio RFX, exploiting the synergy of two test beds, SPIDER and MITICA. SPIDER is dedi…
▽ More
ITER envisages the use of two heating neutral beam injectors plus an optional one as part of the auxiliary heating and current drive system. The 16.5 MW expected neutral beam power per injector is several notches higher than worldwide existing facilities. A Neutral Beam Test Facility (NBTF) was established at Consorzio RFX, exploiting the synergy of two test beds, SPIDER and MITICA. SPIDER is dedicated to develo** and characterizing large efficient negative ion sources at relevant parameters in ITER-like conditions: source and accelerator located in the same vacuum where the beam propagates, immunity to electromagnetic interferences of multiple radio-frequency (RF) antennas, avoidance of RF-induced discharges on the outside of the source. Three years of experiments on SPIDER have addressed to the necessary design modifications to enable full performances. The source is presently under a long shut-down phase to incorporate learnings from the experimental campaign. Parallelly, developments on MITICA, the full-scale prototype of the ITER NBI featuring a 1 MV accelerator and ion neutralization, are underway including manufacturing of in-vessel components, while power supplies and auxiliary plants are already under final testing and commissioning. Integration, commissioning and tests of the 1MV power supplies are essential for this first-of-kind system, unparalleled both in research and industry field. The integrated test to confirm 1MV output by combining invertor systems, DC generators and transmission lines extracted errors/accidents in some components. To realize a concrete system for ITER, solutions for the repair and the improvement of the system were developed. Hence, NBTF is emerging as a necessary facility, due to the large gap with existing injectors, effectively dedicated to identify issues and find solutions to enable successful ITER NBI operations in a time bound fashion.
△ Less
Submitted 4 April, 2023;
originally announced April 2023.